CMI Energy repairing Electrabel plant at Saint-Ghislain (Belgium)
December 05th 2012
CMI Energy has won a new order for the renovation of a heat recovery steam generator at the Electrabel site of Baudour Saint-Ghislain (Mons, Belgium). This boiler was damaged in mid-October following the formation of a gas pocket inside the inlet duct.
CMI Energy proposed a fast and efficient solution for Electrabel. Teams from CMI HRS, the Liège Business Unit of CMI Energy, are currently working seven days a week to rehabilitate this boiler. Repairs should be completed by mid-January of 2013.